Scaffolding construction at Blisterliden wind farm

We have been commissioned by Omexom to carry out substation construction within the Blisterliden wind farm, a strategic project that promotes the development of renewable energy in the region.

Our assignment includes the casting of a slab on ground, foundations for apparatus installations and a transformer pit. For the transformer pit, a watertight casting is carried out where both the slab and the walls are cast in a single continuous casting, which guarantees the highest possible safety and durability of the structure.

The project is under construction and is expected to be finalised in 2025, when the substation will play an important role in ensuring stable and efficient power transmission from the wind farm.

Project facts

Locationblister packs

ClientOmexom

Scope of the programmeScaffolding foundations wind farm

Finalisation2025